Building Expansion News

We are building an extension on our present facility to better reach, teach and minister to our children and children in our community. Visit this page for updates on the project.
To contribute online to this project financially, follow the link and designate your giving as, "Expansion"
March 18, 2013
Progress Update – March 18
There is steady progress, and this stage continues to be particularly exciting as the grey concrete starts to take on its final form with paint, carpet, furnishings... All the colours are looking fantastic!
An update from Ron McArthur, our project manager:
- Dry-walling – it's nearly finished. There is just a bit of work left on the second floor
- Painting – wall painting is progressing well
- Cabinets – storage cabinets have been installed
- Doors have been installed in most rooms
- Flooring – they are installing tile floor in the south foyer, carpet and tile in the main floor rooms
- Stages – Chapel and second floor auditorium are framed. AVL wiring under the stages is underway – then the platforms will be enclosed
- Trusses - installed
Redbox
- On Tuesday, March 12 we met with all our Building Partners (Redbox, Reinders and Hawkey) to plan the installation of Redbox furnishings
- Redbox furnishings arrive the first week of April
- Installation will begin on Monday, April 8 and be finished on Friday, April 19.
- Redbox and Hawkey will install the major furnishings the week of April 8 to 12. One technician from Redbox and 4 to 5 skilled Builders from Hawkey
- Redbox, plus some volunteers from APC, will assemble and place the various furnishings the week of April 15 to 19. One Technician from Redbox and 4 to 5 volunteers
About the Author
Claudette Perry
Claudette Perry is the executive assistant to our Senior Pastor, Keith Smith. She is helping out with our new Children's Building Expansion project by being the liaison between our church staff and the project manager, Ron McArthur.
She has been part of the APC team since August 2009.
March 11, 2013
Progress Update – March 11
We have an exciting update for you today! It's really coming together now and you can really see, from the pictures, how the end is in sight!



From Ron McArthur, project manager:
- Dry-walling – Most rooms in the New Building are completed, Chapel almost complete
- Painting – wall painting is progressing well (see pictures)
- Cabinets – storage cabinets have been installed in most rooms (see pictures)
- Doors – installed in most rooms this week
- Construction of the Stage for the second floor auditorium – framed this week (see pictures)
- Trusses (Metal framing that holds stage lighting and speakers ) – installation underway on second floor
On Tuesday, March 12 all partners (Architect, Hawkey and Redbox) will be here to firm up the plan for all the work activities that need to happen between now and the opening.
Isn't this great? Praise God!
About the Author
Claudette Perry
Claudette Perry is the executive assistant to our Senior Pastor, Keith Smith. She is helping out with our new Children's Building Expansion project by being the liaison between our church staff and the project manager, Ron McArthur.
She has been part of the APC team since August 2009.
January 14, 2013
Progress Update - January 14
The new building continues its steady progress towards completion! Everything is on schedule.
- Passed Inspection –
Plumbing, Mechanical and Electrical - Dry-walling –
starts Monday, January 14 - Framing –
complete in new Building (more work required in the Chapel) - Windows –
any windows that were cracked during shipping have been replaced - Exterior Siding –
underway, scheduled to be completed on Monday, January 14 - Data Cables are being pulled to connect security cameras and computers
- Interior Doors were delivered this week
About the Author
Claudette Perry
Claudette Perry is the executive assistant to our Senior Pastor, Keith Smith. She is helping out with our new Children's Building Expansion project by being the liaison between our church staff and the project manager, Ron McArthur.
She has been part of the APC team since August 2009.
December 18, 2012
Progress Update – December 22
We can report a major milestone! The building is closed in and heated!
- Windows and doors are installed
- Building is secure
- Electrical – connected the new building power to the main circuit breaker
- 90% (plus) of the interior wall framing is complete
- Trip to Redbox Dec 22 (Ron McArthur and Ken Matthews, Hawkey President attended)
- Cabinetry is nearly completed. The finished units are very good quality
- Discussed implementation plans, timelines, prepared a detailed list of action items to be ready
- Very worthwhile meeting
About the Author
Claudette Perry
Claudette Perry is the executive assistant to our Senior Pastor, Keith Smith. She is helping out with our new Children's Building Expansion project by being the liaison between our church staff and the project manager, Ron McArthur.
She has been part of the APC team since August 2009.
